What’s going on?

·         Work is progressing on the atrium, staircase and lifts which you can see in new photographs which have been added to the image gallery.  This area is due to be handed over to the library in early May

·         Demolition work on the ground floor where the new gallery and exhibition space will be located is almost complete and all the existing windows have been removed. This area is expected to be handed over to the library mid June.

·         The 2nd floor of the Tower is on schedule to open week commencing 7th April.  This floor contains the new postgraduate research lounge, the law books, PC desks and soft seating as well as an information point.