BJL redevelopment update 18 April 2013
What’s going on?
·
The book moves
from the third and fourth floors are almost complete and they are now shelved
in their temporary location on the ground floor in the decant area adjacent to
the reception desk. This area will be fully accessible from Monday 22
April
·
There will be a
large floor plan as you go through the doors into the decant space showing the
layout and where the books are shelved. Library staff will be happy to
help users to find the items they are looking for
·
The third and
fourth floor refurbishment is underway and these floors are expected to be
reopened at the end of July
·
The tunnel
through the link between the east and west
buildings has been erected and work has begun on the construction of the atrium
When’s it happening?
·
The ground floor
decant area will be open from Monday 22 April
Work has already begun on the refurbishment of the
third and fourth floors which will be reopened in late July